The Rustic Canyon Recreation Center Pool has not been open for several years. On December 19, Rec and Parks Commissioners will vote to repair it.

At the December 19 meeting of the Board of Recreation and Park Board of Commissioners, the repair of the Rustic Canyon Swimming Pool is on the agenda. After approval of minutes, the general manager’s update and general public comment that approval is the second item listed under Board Reports 24-263.

The meeting will be held at 9 a.m. at El Sereno Recreation Center at 4721 Klamath Street. One can listen virtually, but public comments are taken only in person. To listen to the meeting dial (669) 900-6833 and enter 854 4549 8284, and then press # or go to the link: click here.

In July, CTN reported that eight of the 56 pools operated by RAP were closed, including Rustic Canyon. At that time, RAP Public Information officer Rose Watson said, “The long-term plan for Rustic Canyon pool is to demolish and construct a modern pool facility that will meet the needs of the community. Immediate repairs required for reopening include electrical work, plumbing and pump repairs.”

Watson said there were plans to have the Rustic Pool operational by next summer, unless funding could be secured for a full-pool replacement project.

Now, six months later, the commissioners will vote on spending $210,896 for the rehabilitation of deteriorated mechanical equipment and damaged structures.

About $50,404 of Rustic Canyon Quimby Funds will be used and the remaining funding will come from park fees, which were collected within five miles of Rustic Canyon Recreation Center.

Listed under the scope of work:

  • Disconnect and remove existing two-tank filter system
  • Install and set New Stark Filter System on existing concrete pad
  • Load filter media into new tank system
  • Reconnect existing influent piping
  • Reconnect existing effluent piping
  • Enlarge backwash core located on wall adjacent backwash tank outside of the building
  • Install 6″ backwash pipe from filters to existing backwash tank outside of the building
  • Install pressure amplification system
  • Replace existing 6″ suction pipe on existing pool pump
  • Replace Stenner 85M2 Chemical Pump

The timeline for bids and the award is December 2024 through March 2025. Construction is tentatively planned for April 2025 through August 2025, and post construction is slated for September 2025 through February 2026.

To view the document online: visit: click here.

 

Share Story :
RSS
Follow by Email
Facebook
Twitter
This entry was posted in Parks. Bookmark the permalink.

One Response to It’s Up for a Vote to Repair Rustic Canyon Pool

  1. Cindy Simon says:

    I’ll believe it when I see it

Leave a Reply

Your email address will not be published. Required fields are marked *